News

Entergy's Louisiana unit received the state's regulatory approval to move forward with infrastructure investments tied to ...
Louisiana utility regulators approved a plan Wednesday, August 20, 2025 to install three natural-gas fueled power plants for the tech company Meta, which needs the electricity for ...
Meta’s data center will need about three times the amount of electricity that New Orleans uses in a year and increase Entergy ...
If the Public Service Commission approves the plan, Entergy will have the greenlight to build three new gas plants to power ...
Louisiana utility regulators on Wednesday approved Entergy Louisiana’s plan to build new natural gas plants and transmission ...
Fast-tracking a vote that was originally expected to happen two months from now, state utility regulators plan to decide ...
Louisianas Public Service Commission approved Entergys proposal to build three combined-cycle gas turbines and supporting transmission infrastructure to power Metas $10 billion AI data center in ...
Entergy Louisiana has received the green light to move forward with its plan to power Meta's massive $10 billion data center in North Louisiana. The Louisiana Public Service Commission (PSC), the body ...
Louisiana Public Service Commissioners voted four to one to approve Entergy’s three new gas plants to power Meta’s largest-ever data center.
Louisiana utility regulators have cleared the way for Entergy Louisiana to build new natural gas plants and transmission lines to support Meta’s planned $10 billion data center in Richland Parish, The ...
Certain homes in a tiny part of northern Louisiana have more than doubled in price thanks to a major move by Mark Zuckerberg, the CEO of Meta.
The Louisiana Public Service Commission voted 4-1 to approve Entergy’s plan to build three natural gas power plants for Meta’s $800M data center in Richland Parish ...